Building Updates
Phase I
10/21/24 Update
Equipment Updates
EQUIPMENT LIST | ORDERED | IN FACILITY | COMMISSIONED | OPERABLE |
---|---|---|---|---|
Novellus C1 PECVD | ||||
Expertech CTR-200 LPCVD [Si] | ✓ | ✓ | ||
Expertech CTR-200 LPCVD [Oxide] | ✓ | ✓ | ||
Expertech CTR-200 [N2 Anneal] | ✓ | ✓ | ||
Expertech CTR-200 [POCl3] | ✓ | ✓ | ||
Lam 590 RIE [Si] | ✓ | ✓ | ||
Lam 490 RIE [Oxide] | ✓ | ✓ | ||
Kurt J. Lesker PVD 200 | ||||
Onto Innovation Inspectrology IVS200 | ✓ | ✓ | ||
Woollam RC2XF Elipsometer | ✓ | ✓ | ✓ | |
Matrix Model 106 Asher | ✓ | ✓ | ||
Nikon iLine NSR 2005i8 Stepper | ✓ | ✓ | ||
Obducat MC204 Coater/Developer | ✓ | ✓ | ✓ | |
Obducat MC204 Wet Cleaner | ✓ | ✓ | ✓ | |
Centrotherm c.ACTIVATOR 150-50 | ✓ | ✓ | ||
Centrotherm c.OXIDATOR 150-50 | ✓ | ✓ |
Phase II
10/21/24 Update
Clean Room Wall Installation Start
ESD Flooring Start
RO/DI Asahi Pipe Training
Exhaust Duct Drop Fabrication
10/14/24 Update
Prepping for Clean Room Walls and ESD Flooring
Overhead CPVC & Stainless Ductwork in Clean Rooms
ACM Panel Install Completed
Water Test R1 Completed (Passed)
10/7/24 Update
Cleanroom Ceiling Grid Started
Overhead MEP Install Ongoing
Electrical Room Buildout/Wire Pulls
Generator Install
9/23/24 Update
Cleanroom Ceiling Grid Hangers Started
Overhead MEP Install Ongoing
Mechanical Terminal Unit Installation
Mechanical Yard Equipment Pads
9/16/24 Update
Overhead House Gas Piping Install Ongoing
Initial Coat of Paint in Offices Complete
Office Ceiling Grid Started
8/26/24 Update
Preliminary Water Test at Penetrations (Pass)
Overhead MEPs Ongoing
Painting at Bulkheads and Mechanical Room Walls
Prep for AHU-3 Setting to Low Roof
8/19/24 Update
Roof Coping Cap Complete
Overhead MEPs Ongoing
Drywall Finishing Ongoing
Finalizing IMP Penetration Details
8/12/24 Update
Roof Coping Cap Ongoing
Overhead MEPs Ongoing – Stainless Duct Fab Started
AHU 1-3 Delivery
ACM Mock-up Complete – Working on Corrections
8/5/24 Update
Roof Coping Cap Delivery
Overhead MEPs Ongoing
Paint Complete at East Corridor Top-out
Exterior Glazing Delivery & Install Start
7/29/24 Update
ACM Panel Install 50% Complete
Overhead MEPs Continued
Office Area Overhead Rough 75% Complete
Paint Complete at Corridor Walls/Bulkheads
7/22/24 Update
IMPs Complete – Detailing Ongoing at Penetrations
Overhead MEP Continued
Closed in Office Area Walls
Tape, Mud, & First Coat Interior Walls
7/15/24 Update
West Elevation IMP Complete
Overhead MEP Ongoing
Admin Area In-Wall Rough Sign-Off
ACM Panels Start
7/8/24 Update
South Side IMP Complete
Overhead MEP Start
Clean Room Unistrut Supports Completed
Office In-Wall Rough-In Ongoing
6/17/24 Update
East Side IMP Complete, South Side IMP 75% Complete
All TPO Roofing Complete
North Corridor Sheetrocked, Finished, Painted at Top-out
North Corridor MEP Hangers Commenced
6/10/24 Update
North Side IMP Complete
High Roof Install 100% Complete
Low Roof Install Ongoing
Cleanroom Bulkhead Sheetrock Finishing Started
6/3/24 Update
North Side IMP Approaching Completion
High Roof Install 75% Complete
Interior Office Framing Complete
Cleanroom Bulkhead Framing Started
5/28/24 Update
North Side Roofing Started
IMP Installation Ongoing
Interior Office Framing Started
Offsite MEP Pre-Fabrication Beginning
5/20/24 Update
Exterior Framing Complete for North, East, South Elevations
IMWP Installation Commenced
Structural Steel Complete
Thermal Coating Installation
5/13/24 Update
Decking Dryfall Complete
Exterior Framing and Blocking Complete North Elevation
Welded MEP Hangers Complete
Office/Admin Area MEP Hangers Layout
5/6/24 Update
Building Ground/Lightning Protection Continued
Begin Exterior Framing
Building Deck Dryfall Paint
Begin Welded MEP Hangers to Steel
4/29/24 Update
Building Ground/Lightning Protection Rough-in
Column Baseplate Concrete Pourbacks
Decking Installation Complete
Building Eyebrow Steel & Final Braced Frame Welds Ongoing
4/22/24 Update
Temporary Power Ran & Panel Energized
Grouting Column Baseplates
Decking Installation Commencing
4/15/24 Update
Steel Erection Substantially Complete
Structural Steel Detailing Started
Exterior Framing Procurement Released
4/08/24 Update