Building Updates
Phase I
12/23/24 Update
Equipment Updates
EQUIPMENT LIST | ORDERED | IN FACILITY | COMMISSIONED | OPERABLE |
---|---|---|---|---|
Novellus C1 PECVD | ✓ | ✓ | ||
Expertech CTR-200 LPCVD [Si] | ✓ | ✓ | ||
Expertech CTR-200 LPCVD [Oxide] | ✓ | ✓ | ||
Expertech CTR-200 [N2 Anneal] | ✓ | ✓ | ||
Expertech CTR-200 [POCl3] | ✓ | ✓ | ||
Lam 590 RIE [Si] | ✓ | ✓ | ||
Lam 490 RIE [Oxide] | ✓ | ✓ | ||
Kurt J. Lesker PVD 200 | ||||
Onto Innovation Inspectrology IVS200 | ✓ | ✓ | ||
Woollam RC2XF Elipsometer | ✓ | ✓ | ✓ | |
Matrix Model 106 Asher | ✓ | ✓ | ||
Nikon iLine NSR 2005i8 Stepper | ✓ | ✓ | ✓ | |
Obducat MC204 Coater/Developer | ✓ | ✓ | ✓ | |
Obducat MC204 Wet Cleaner | ✓ | ✓ | ✓ | |
Centrotherm c.ACTIVATOR 150-50 | ✓ | ✓ | ||
Centrotherm c.OXIDATOR 150-50 | ✓ | ✓ |
Phase II
12/23/24 Update
Mechanical Room Overhead Pipe Complete
Mechanical Room Equipment Being Set
AHU Piping Install Started
Gas Bunker Exterior Panels Started
12/16/24 Update
Mechanical Yard Piping Install Started
Clean Room Overhead MEP Install Ongoing
FCU Final Connections and Writing
Mechanical Room Pipe Install Started
12/09/24 Update
Clean Room Demising Walls Complete
Clean Room Overhead MEP Install Ongoing
FCU Final Connections and Writing
Mechanical Room Pipe Install Started
11/25/24 Update
Clean Room Demising Walls Continued
Overhead Clean Room Rough-in
AHU Pad Pours
Final ACM Caulking
11/18/24 Update
Clean Room Demising Wall Install
Overhead Clean Room ASSD Rough-in
Mechanical Yard Pad Prep
Chillers 1 & 2 Set
11/11/24 Update
Clean Room Containment Complete
First Super Clean Complete
Controls Conduit Rough-in
Clean Room Protocol Level 2
11/4/24 Update
Clean Room Perimeter Walls Complete
ESD Floor Complete
Interstitial Lights Burning
First Super Clean Ongoing
10/21/24 Update
Clean Room Wall Installation Start
ESD Flooring Start
RO/DI Asahi Pipe Training
Exhaust Duct Drop Fabrication
10/14/24 Update
Prepping for Clean Room Walls and ESD Flooring
Overhead CPVC & Stainless Ductwork in Clean Rooms
ACM Panel Install Completed
Water Test R1 Completed (Passed)
10/7/24 Update
Cleanroom Ceiling Grid Started
Overhead MEP Install Ongoing
Electrical Room Buildout/Wire Pulls
Generator Install
9/23/24 Update
Cleanroom Ceiling Grid Hangers Started
Overhead MEP Install Ongoing
Mechanical Terminal Unit Installation
Mechanical Yard Equipment Pads
9/16/24 Update
Overhead House Gas Piping Install Ongoing
Initial Coat of Paint in Offices Complete
Office Ceiling Grid Started
8/26/24 Update
Preliminary Water Test at Penetrations (Pass)
Overhead MEPs Ongoing
Painting at Bulkheads and Mechanical Room Walls
Prep for AHU-3 Setting to Low Roof
8/19/24 Update
Roof Coping Cap Complete
Overhead MEPs Ongoing
Drywall Finishing Ongoing
Finalizing IMP Penetration Details
8/12/24 Update
Roof Coping Cap Ongoing
Overhead MEPs Ongoing – Stainless Duct Fab Started
AHU 1-3 Delivery
ACM Mock-up Complete – Working on Corrections
8/5/24 Update
Roof Coping Cap Delivery
Overhead MEPs Ongoing
Paint Complete at East Corridor Top-out
Exterior Glazing Delivery & Install Start
7/29/24 Update
ACM Panel Install 50% Complete
Overhead MEPs Continued
Office Area Overhead Rough 75% Complete
Paint Complete at Corridor Walls/Bulkheads
7/22/24 Update
IMPs Complete – Detailing Ongoing at Penetrations
Overhead MEP Continued
Closed in Office Area Walls
Tape, Mud, & First Coat Interior Walls
7/15/24 Update
West Elevation IMP Complete
Overhead MEP Ongoing
Admin Area In-Wall Rough Sign-Off
ACM Panels Start
7/8/24 Update
South Side IMP Complete
Overhead MEP Start
Clean Room Unistrut Supports Completed
Office In-Wall Rough-In Ongoing
6/17/24 Update
East Side IMP Complete, South Side IMP 75% Complete
All TPO Roofing Complete
North Corridor Sheetrocked, Finished, Painted at Top-out
North Corridor MEP Hangers Commenced
6/10/24 Update
North Side IMP Complete
High Roof Install 100% Complete
Low Roof Install Ongoing
Cleanroom Bulkhead Sheetrock Finishing Started
6/3/24 Update
North Side IMP Approaching Completion
High Roof Install 75% Complete
Interior Office Framing Complete
Cleanroom Bulkhead Framing Started
5/28/24 Update
North Side Roofing Started
IMP Installation Ongoing
Interior Office Framing Started
Offsite MEP Pre-Fabrication Beginning
5/20/24 Update
Exterior Framing Complete for North, East, South Elevations
IMWP Installation Commenced
Structural Steel Complete
Thermal Coating Installation
5/13/24 Update
Decking Dryfall Complete
Exterior Framing and Blocking Complete North Elevation
Welded MEP Hangers Complete
Office/Admin Area MEP Hangers Layout
5/6/24 Update
Building Ground/Lightning Protection Continued
Begin Exterior Framing
Building Deck Dryfall Paint
Begin Welded MEP Hangers to Steel
4/29/24 Update
Building Ground/Lightning Protection Rough-in
Column Baseplate Concrete Pourbacks
Decking Installation Complete
Building Eyebrow Steel & Final Braced Frame Welds Ongoing
4/22/24 Update
Temporary Power Ran & Panel Energized
Grouting Column Baseplates
Decking Installation Commencing
4/15/24 Update
Steel Erection Substantially Complete
Structural Steel Detailing Started
Exterior Framing Procurement Released
4/08/24 Update
Steel Erection Started 4/01/24
SOG FF/FL Testing & Quality Control Scan
BIM Model Population Nearing Completion
Staff

Administrator
Lauryn Adkins

Workforce Development Director
Shawn Bell

Facilities & Process Engineer
Nestor Camargo

Faculty Director
Zhong Chen

Managing Director
Shannon G. Davis

Workforce Development Lead
Jeff Dix

Executive Director
H. Alan Mantooth

Facility Process Engineer
Tanner Rice

Technical Director
Greg Salamo

Fabrication Director
Thomas White
Contact


